Schedule

 We welcome and encourage community participation and are committed to keeping you informed of the project timeline and opportunities for public engagement.  Please check back here regularly for an updated schedule of milestones, events and notices - and sign up to receive our email updates!

Project Milestones

Graphic for website.png

Spring 2024

  • A 2-day road closure (March 21-22)  is necessary as the on-site crane is dismantled.

​​

Fall 2023/Spring 2024

  • Construction will required a partial street closure of Date Avenue beginning November 27, 2023.  The street will be closed from 7:00 a.m. to noon every day - except Sunday.  This schedule will continue through March 2024.  Sidewalks adjacent to the property will also be closed, along with the adjacent MTS bus stop.

 

Summer 2022

  • Construction Begins on Date Avenue between Orange and Allison Avenues (Aug-Sept).

Fall 2021